Technologies: Electrical

Federal Bureau of Investigations (FBI) Criminal Justice Information services (CJIS) Division Complex Campus Paving, Repair and Maintenance in Clarksburg, West Virginia 

Meltech completed this project for the Federal Bureau of Investigations (FBI) Criminal Justice Information Services (CJIS) Division Complex Campus Paving, Repair and Maintenance project in Clarksburg, West Virginia. 

This work was completed on the CJIS Campus. The campus location is on approximately 35 acres of asphalt pavement that includes parking areas, roadways, docks, access driveways and walking paths. The site pavement is original to its construction in 1993-1994. Multiple areas of exposed coarse aggregate with noticeable spider cracks throughout the wearing course were identified in this project for repair. The roadway from the East Gate to the Child Development Center (CDC) also had visible cracking along the cold joints where the original paving passes stopped and started. The shoulders along this road were eroded and also required restoration. Several drop inlets (drains) had identified failing concrete basins that required repair to continue proper drainage of the parking lots. The concrete damage posed safety concerns for the campus and required repairs in order to ensure safe activities in the area. 

Meltech developed a work plan and method of execution for the work in accordance with the design package. The work plan included a schedule, phasing plan, submittals, QC Plan, Traffic Control plan, Asphalt Testing plan and a Millings Disposal plan. Each plan submitted required approval prior to construction. The project also required several safety plans prior to start. Meltech management worked directly with our safety department to complete the Environmental Protection Plan, Accident and Prevention Plan (APP), Activity Hazard Analysis (AHA), Crane Critical Lift Plan with proof of qualification for crane operators, Indoor Air Quality Management Plan (IAQ), Construction Site Plan, Traffic Control plan, Waste Management Plan, 

The work included approximately 67,220 sq. yds. of repair work. Majority of the work was concentrated on the wearing course. The wearing coursed required 1-1/2” to 2” to be milled and overlaid with 1-1/2” to 2” of new asphalt. A total of 6 catch basins were identified for repairs. There was approximately 2460 SF of full depth repair and other miscellaneous repairs completed with the project package. 

Understanding the work identified in this project as asphalt repair, Meltech immediately recognized the need to complete this work prior to the start of winter. This project was completed for multiple parking lots, access drives, walking paths and other areas of occupancy. Being an occupied facility Meltech understood the work had to be coordinated with the daily activities of the campus. With these considerations in mind, Meltech submitted a fast-tracked schedule to complete the work in after hours, weekends and in double shift. This work was completed in half the time and included 2 additional modifications for an addition of shoulder stone and other miscellaneous items; for a contract completion of an entire 6 months early.  

Short description: Federal Bureau of Investigations (FBI) Criminal Justice Information services (CJIS) Division Complex Campus Paving, Repair and Maintenance in Clarksburg, West Virginia  Meltech completed this project for the Federal Bureau of Investigations (FBI) Criminal Justice Information Services (CJIS) Division Complex Campus Paving, Repair and Maintenance project in Clarksburg, West Virginia.  This work was completed on the […]

Short description: Federal Bureau of Investigations (FBI) Design Build Construction Services for the Courtyard Renovations at the J Edgar Hoover FBI Building Headquarters in Washington, DC This project was for the Federal Bureau of Investigations (FBI) Design Build Construction Services for the Courtyard Renovations at the J Edgar Hoover Headquarters in Washington, DC. The current courtyard has […]

Short description: NAVFAC Quantico Marine Corp Child Development Center HVAC Repairs in Quantico, Virginia Meltech completed this project for the Naval Facilities Engineering Command Washington for the repairs to the HVAC systems at the Child Development Center at the Quantico Marine Corp Base in Quantico, Virginia.

Short description: NAVFAC Quantico Marine Corp Base Substation Repairs at the ICS & Larson Gym in Quantico, Virginia Meltech completed this project for electrical repairs to the substation at the ICS and Larsons Gym at the Quantico Marine Corp Base in Quantico, Virginia. Larson’s Gym started life as an aircraft hangar in the 1930s as the current […]

Short description: NAVFAC Quantico Marine Corp Base Building 3228 in Quantico, Virginia General Synopsis Meltech completed this project for the Naval Facilities Engineering Command Washington for the replacement of the modular office and installation of a new mezzanine at Building 3228 at Quantico Marine Corps Base in Quantico, Virginia. The project was completed in 3 phases: Phase […]

Short description: NAVFAC Quantico Marine Corp Base Butler Stadium in Quantico, Virginia Meltech responded to the emergency request for the NAVFAC Quantico Marine Corp Base for the repairs to faulted circuits at the Butler Stadium.

Short description: NAVFAC Quantico Marine Corp Base Officer’s Candidate School (OCS) Parade Deck in Quantico, Virginia General Synopsis Meltech completed this important project for the Naval Facilities Engineering Command (NAVFAC) Washington at the Quantico Marine Corp Base in Quantico, Virginia for the renovations and repairs to the reviewing stand at the Officer’s Candidate School (OCS) Parade Deck. […]

Short description: NAVFAC Walter Reed National Military Medical Center Building 62 Tranquil Hall Living Suites The project was for interior construction, interior finishes, plumbing and selective building demolition. The project was to provide replacement ABA/ADA plumbing fixtures in Building 62 Tranquil Hall Movie Room and Gathering Place Austin’s Playroom Lobby & Warrior Café and living suites, bathrooms […]

Short description: NAVFAC Replace Steam & Condensate Piping at Walter Reed National Military Medical Center in Bethesda, Maryland General Synopsis Meltech completed this project for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. This project was for the replacement of the steam and condensate piping to Buildings 11, […]

Short description: NAVFAC Walter Reed National Military Medical Center Convert Part of Warehouse Building 226 to Auxillary Gym in Bethesda, Maryland Meltech completed this important project for the Naval Facilities Engineering Command Washington for the conversion of part of Building 226 warehouse to an auxillary gym. This work was completed at the Walter Reed National Military Medical […]